Crown Street Upgrade

Weekly Project Updates

  • Construction update for week commencing 15 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).

    Our construction work for the week commencing 15 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue kerb and gutter works and commence footpath excavation.
    • From Oxford Street to Albion Street – trees installation
    • From Davies Street to Devonshire Street – commence kerb and gutter works and continue electrical work for light poles installation.

    Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team