Crown Street Upgrade

Weekly Project Updates

November 2023

  • Construction update for week commencing 11 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 11 December 2023, weather permitting, includes: Continue drainage works Continue kerb stone, concrete gutter and footpath works We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration of...
  • Construction update for week commencing 04 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 04 December 2023, weather permitting, includes: Commence drainage works Continue kerb and gutter works We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration of works to assist pedestr...
  • Construction update for week commencing 27 November 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 27 November 2023, weather permitting, includes: Commence excavation of existing road and kerb and gutter. Commence footing works. We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration ...
  • Construction update for week commencing 20 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street will end on Wednesday and our team will move to next section between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 20 November 2023, weather permitting, includes: Continue footing work between Oxford Street and Little Oxford Street. Complete work to dismantle temporary materials/equipment storage areas ahead of scheduled break in construction (Campbell Street - Oxford Street sect...
  • Construction update for week commencing 13 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 13 November 2023, weather permitting, includes: 24 hour road closure at Arnold Pl intersection with Crown Street until 19 November for CFT construction Flexi pave installation in tree beds at Crown Street between Campbell Street and Goulburn Street – temporary closure of outdoor dining spaces may be required. Start work to dismantle temporary materials/e...
  • Construction update for week commencing 06 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 06 November 2023, weather permitting, includes: Continue footing works at Crown Street between Campbel Street and Goulburn Street and between Oxford Street and Little Oxford Street 24 hour road closure at Taggarts Lane intersection with Crown Street from 8 November until 11 November with detour via Little Oxford Street, Denham Street and Campbell Street ...