Crown Street Upgrade

Weekly Project Updates

  • Construction update for week commencing 11 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 11 March 2024 weather permitting includes:

    • From Albion Street to Campbell Street – commence footpath works and continue kerb, gutter and footings for light pole installation.
    • From Oxford Street to Albion Street – light pole installation.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team