Crown Street Upgrade

Weekly Project Updates

  • Construction update for week commencing 25 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 25 March 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue footpath, kerb and gutter works.
    • From Albion Street to Campbell Street – work on stormwater pipes near pedestrian crossing.
    • From Oxford Street to Albion Street – continue work on Telstra pits.

    No work will take place during the Easter Long Weekend.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team