    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 30 October 2023, weather permitting, includes:

    • Continue kerb, gutter and garden bed on Crown Street between Campbel Street and Goulburn Street
    • Continue footings for smartpole between Oxford Street and Little Oxford Street

    Paving to be rescheduled for finishing works in coming weeks at Taggarts Lane.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.