Deborah and IsabelCommunity Team
Sydney CivilPhone: 1300 997 858
Email: community@sydneycivil.com
Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).
Our construction work for the week commencing 01 July 2024 weather permitting includes:
Temporary access changes for Shannon Reserve (park and playground) During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.
Temporary relocation of southbound bus stop During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you, Crown Street Upgrade project team |
Dear stakeholder,
Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).
Our construction work for the week commencing 24 June 2024 weather permitting includes:
Temporary access changes for Shannon Reserve (park and playground) During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.
Temporary relocation of southbound bus stop During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.
Shannon Reserve access changes and bus stop relocation from Wednesday 26 June. |
|
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you, Crown Street Upgrade project team |
Construction works continue at Crown Street between Albion Street to Foveaux Street (east), between Albion Street to Campbell Street (west) and between Foveaux Street to Fitzroy Street (west). We will commence work between Foveaux Street to Collins Street (alongside Shannon Reserve).
Our construction work for the week commencing 17 June 2024 weather permitting includes:
Temporary access changes for Shannon Reserve (park and playground) During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.
Temporary relocation of southbound bus stop During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.
Shannon Reserve access changes and bus stop relocation from Wednesday 26 June. |
|
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you, Crown Street Upgrade project team |
Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west) and will commence between Foveaux Street to Fitzroy Street (west).
Our construction work for the week commencing 10 June 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
|
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you, Crown Street Upgrade project team |
Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).
Our construction work for the week commencing 03 June 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).
Our construction work for the week commencing 27 May 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).
Our construction work for the week commencing 13 May 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
|
Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).
Our construction work for the week commencing 06 May 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street to Campbell Street and between Davies Street to Devonshire Street (east). Our team is also ready to start section between Fitzroy Street to Foveaux Street (east).
Our construction work for the week commencing 29 April 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).
Our construction work for the week commencing 22 April 2024 weather permitting includes:
Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).
Our construction work for the week commencing 15 April 2024 weather permitting includes:
Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street. We are also starting works from Davies Street to Devonshire Street (east).
Our construction work for the week commencing 08 April 2024 weather permitting includes:
Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Our construction work for the week commencing 02 April 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
Our construction work for the week commencing 25 March 2024 weather permitting includes:
No work will take place during the Easter Long Weekend.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
Our construction work for the week commencing 18 March 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
Our construction work for the week commencing 11 March 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue at Crown Street between Albion Street to Fitzroy Place and will commence between Albion Street and Campbell Street.
Our construction work for the week commencing 04 March 2024 weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works are continuing Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
Our construction work for the week commencing 26 February 2024, weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works continue on Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
Our construction work for the week commencing 19 February 2024, weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
Our construction work for the week commencing 12 February 2024, weather permitting includes:
Note: we are planning for a two week closure of Clifton Reserve starting Monday 19 February, subject to approvals. Please contact the team if you are a resident and require a parking permit.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
Our construction work for the week commencing 05 February 2024, weather permitting includes:
Note: we are planning for a two week closure of Clifton Reserve starting Monday 19 February, subject to approvals. Please contact the team if you are a resident and require a parking permit.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.
Our construction work for the week commencing 22 January 2024, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.
Our construction work for the week commencing 15 January 2024, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Campbell Street and Clifton Reserve.
Our construction work for the week commencing 8 Juanuay 2024, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
We wish you and your loved ones a safe and happy holiday season. We look forward to a productive 2024 working with the Crown Street community.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 354 Crown Street and Clifton Reserve.
Our construction work for the week commencing 18 December 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
From 6pm Friday 22 December to Monday 08 January 2024 our project site and offices will be closed over the holiday period.
We wish you and your loved ones a safe and happy holiday season. We look forward to a productive 2024 working with the Crown Street community.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 354 Crown Street and Clifton Reserve.
Our construction work for the week commencing 11 December 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 354 Crown Street and Clifton Reserve.
Our construction work for the week commencing 04 December 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between 354 Crown Street and Clifton Reserve.
Our construction work for the week commencing 27 November 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street will end on Wednesday and our team will move to next section between 354 Crown Street and Clifton Reserve.
Our construction work for the week commencing 20 November 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 13 November 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 06 November 2023, weather permitting, includes:
Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 30 October 2023, weather permitting, includes:
Paving to be rescheduled for finishing works in coming weeks at Taggarts Lane.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 23 October 2023, weather permitting, includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 16 October 2023, weather permitting, includes:
PROGRESS OF WORKS:
Oxford to Campbell, October 2023
Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 09 October 2023, weather permitting, includes:
Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
We are currently working along the southbound parking lane and footpath between 288 Crown Street and Campbell Street.
Our construction work for the week commencing 4 September 2023, weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Residential access will be available during the Taggarts Lane temporary road closure, as well as access for Zest Apartments carpark and garbage collection.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Thank you,
Crown Street Upgrade team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing. We are currently working along the southbound parking lane between Little Oxford Street and Taggarts Lane.
Our construction work for the week commencing 7 August 2023, weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated.
Please get in touch with the Community Liaison team with any questions or concerns.
Regards,
Community Liaison Team
Construction works on Crown Street between Oxford Street and Campbell Street are continuing.
Our construction work for the week commencing 24 July 2023, weather permitting includes:
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.
For more information visit the Crown Street Upgrade website.
Your patience and cooperation during this period are much appreciated. Please get in touch with the Community Liaison team with any questions or concerns.
Kind regards,
Community Liaison Team
Construction works on Crown Street between Oxford Street and Campbell Street will commence on Monday 17 July 2023.
We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to vehicle parking, changes to pedestrian access and temporary lane closures.
Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, and business and car users. Please follow the directions of traffic controllers at all times.
Your patience and cooperation during this period are much appreciated.
Phone: 1300 997 858
Email: community@sydneycivil.com