Crown Street Upgrade

Weekly Project Updates

  • Construction update - Week commencing 01 July 2024

    Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).
  • Construction update - Week commencing 24 June 2024

    Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).
  • Construction update for week commencing 17 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east), between Albion Street to Campbell Street (west) and between Foveaux Street to Fitzroy Street (west). We will commence work between Foveaux Street to Collins Street (alongside Shannon Reserve).
  • Construction update for week commencing 10 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west) and will commence between Foveaux Street to Fitzroy Street (west).
  • Construction update for week commencing 03 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).
  • Construction update for week commencing 27 May 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).
  • Construction update for week commencing 13 May 2024

    Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).  
  • Construction update for week commencing 06 May 2024

    Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).
  • Construction update for week commencing 29 April 2024

    Construction works continue at Crown Street between Albion Street to Campbell Street and between Davies Street to Devonshire Street (east). Our team is also ready to start section between Fitzroy Street to Foveaux Street (east).
  • Construction update for week commencing 22 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).
  • Construction update for week commencing 15 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).
  • Construction update for week commencing 08 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street. We are also starting works from Davies Street to Devonshire Street (east).
  • Construction update for week commencing 02 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
  • Construction update for week commencing 25 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
  • Construction update for week commencing 18 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
  • Construction update for week commencing 11 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.
  • Construction update for week commencing 04 March 2024

    Construction works continue at Crown Street between Albion Street to Fitzroy Place and will commence between Albion Street and Campbell Street.
  • Construction update for week commencing 26 February 2024

    Construction works are continuing on Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
  • Construction update for week commencing 19 February 2024

    Construction works continue on Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
  • Construction update for week commencing 12 February 2024

    Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
  • Construction update for week commencing 05 February 2024

    Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.
  • Construction update for week commencing 22 January 2024

    Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.
  • Construction update for week commencing 15 January 2024

    Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.
  • Construction update for week commencing 8 January 2024

    Construction update for week commencing 8 January 2024
  • Construction update for week commencing 18 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 18 December 2023, weather permitting, includes: Continue roadway and footpath works Commence paving footpath works We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration of works to ass...
  • Construction update for week commencing 11 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 11 December 2023, weather permitting, includes: Continue drainage works Continue kerb stone, concrete gutter and footpath works We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration of...
  • Construction update for week commencing 04 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 04 December 2023, weather permitting, includes: Commence drainage works Continue kerb and gutter works We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration of works to assist pedestr...
  • Construction update for week commencing 27 November 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 27 November 2023, weather permitting, includes: Commence excavation of existing road and kerb and gutter. Commence footing works. We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Traffic control will be available on site for the duration ...
  • Construction update for week commencing 20 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street will end on Wednesday and our team will move to next section between 354 Crown Street and Clifton Reserve. Our construction work for the week commencing 20 November 2023, weather permitting, includes: Continue footing work between Oxford Street and Little Oxford Street. Complete work to dismantle temporary materials/equipment storage areas ahead of scheduled break in construction (Campbell Street - Oxford Street sect...
  • Construction update for week commencing 13 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 13 November 2023, weather permitting, includes: 24 hour road closure at Arnold Pl intersection with Crown Street until 19 November for CFT construction Flexi pave installation in tree beds at Crown Street between Campbell Street and Goulburn Street – temporary closure of outdoor dining spaces may be required. Start work to dismantle temporary materials/e...
  • Construction update for week commencing 06 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 06 November 2023, weather permitting, includes: Continue footing works at Crown Street between Campbel Street and Goulburn Street and between Oxford Street and Little Oxford Street 24 hour road closure at Taggarts Lane intersection with Crown Street from 8 November until 11 November with detour via Little Oxford Street, Denham Street and Campbell Street ...
  • Construction update for week commencing 30 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 30 October 2023, weather permitting, includes: Continue kerb, gutter and garden bed on Crown Street between Campbel Street and Goulburn Street Continue footings for smartpole between Oxford Street and Little Oxford Street Paving to be rescheduled for finishing works in coming weeks at Taggarts Lane. We will work to minimise impacts during this time, h...
  • Construction update for week commencing 23 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 23 October 2023, weather permitting, includes: Reopening of Taggarts Lane Continue excavation and prepare base for kerb and gutter on Crown Street between Campbel Street and Goulburn Street Commence footings for smartpole between Oxford Street and Little Oxford Street and between Goulburn Street and Arnold Pl We will work to minimise impacts durin...
  • Construction update for week commencing 16 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 16 October 2023, weather permitting, includes: 24 hour road closure at Taggarts Lane entrance from Crown Street until 30 October with detours via Little Oxford St, Denham St and Campbell St in place Continue drainage works within Taggarts Lane closure and commence CFT works. Commence paving works between Goulburn Street and Arnold Pl Continue excavation...
  • Construction update - Week commencing 09 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. Our construction work for the week commencing 09 October 2023, weather permitting, includes: 24 hour road closure at Taggarts Lane entrance from Crown Street until 30 October with detours via Little Oxford St, Denham St and Campbell St in place Continue drainage works within Taggarts Lane closure Continue excavation and prepare base for existing kerb, gutter and roadway between Goulburn Street and ...
  • Construction work update - week commencing 4 September 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. We are currently working along the southbound parking lane and footpath between 288 Crown Street and Campbell Street. Our construction work for the week commencing 4 September 2023, weather permitting includes: Continue partial footway, kerb and gutter works between Taggarts Lane and Campbell Street Continue paving from corner of Little Oxford Street to Campbell Street 24 hour road closure at Taggart...
  • Our construction work for the week commencing 7 August 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. We are currently working along the southbound parking lane between Little Oxford Street and Taggarts Lane.
  • Construction work update week of 24 July 2023

    Construction work update week of 24 July 2023
  • Our construction work for the week commencing 17 July 2023

    Construction works on Crown Street between Oxford Street and Campbell Street will start on Monday 17 July 2023.