Crown Street Upgrade

Weekly Project Updates

  • Construction update - Week commencing 01 July 2024

    Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).

    Our construction work for the week commencing 01 July 2024 weather permitting includes:

    • From Albion Street to Campbell Street (outside 285A Crown Street) – continue paving works.
    • From Foveaux Street to Fitzroy Street - continue electrical work and kerb and gutter work.
    • Foveaux Street to Collins Street (alongside Shannon Reserve) - kerb and gutter work.

    Temporary access changes for Shannon Reserve (park and playground)

    During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.

    Temporary relocation of southbound bus stop

    During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade project team

  • Construction update - Week commencing 24 June 2024

    Dear stakeholder,

    Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).

    Our construction work for the week commencing 24 June 2024 weather permitting includes:

    • From Albion Street to Campbell Street (outside 285A Crown Street) – asphalt road, footpath and paving works.
    • From Foveaux Street to Fitzroy Street - continue electrical work.
    • Foveaux Street to Collins Street (alongside Shannon Reserve) - continue electrical work.

    Temporary access changes for Shannon Reserve (park and playground)

    During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.

    Temporary relocation of southbound bus stop

    During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.

    Shannon Reserve access changes and bus stop relocation from Wednesday 26 June.

  • Construction update for week commencing 17 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east), between Albion Street to Campbell Street (west) and between Foveaux Street to Fitzroy Street (west). We will commence work between Foveaux Street to Collins Street (alongside Shannon Reserve).

    Our construction work for the week commencing 17 June 2024 weather permitting includes:

    • From Fitzroy Pl to Fitzroy Street – paving and asphalt works.
    • From Albion Street to Campbell Street (outside 285A Crown Street) – continue electrical works for lighting poles installation, continue drainage and kerb and gutter works.
    • From Foveaux Street to Fitzroy Street - electrical works for lighting poles installation.
    • Foveaux Street to Collins Street (alongside Shannon Reserve) - site set up and electrical work.

    Temporary access changes for Shannon Reserve (park and playground)

    During our works please access Shannon Reserve via Collins Street, Richards Lane or Foveaux Street. We will have access points on Crown Steet closed to ensure community and worker safety. See the map below.

    Temporary relocation of southbound bus stop

    During our works we will temporarily relocate the southbound bus stop further south of Collins Street. Please follow signage in the area for more details. See the map below.

    Shannon Reserve access changes and bus stop relocation from Wednesday 26 June.

  • Construction update for week commencing 10 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west) and will commence between Foveaux Street to Fitzroy Street (west).

    Our construction work for the week commencing 10 June 2024 weather permitting includes:

    • From Fitzroy Pl to Fitzroy Street – footpath, paving and asphalt works.
    • From Albion Street to Campbell Street (outside 285A Crown Street) – continue electrical works for lighting poles installation and commence drainage works.
    • From Foveaux Street to Fitzroy Street - start site set-up including parking changes and light pole installation works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

  • Construction update for week commencing 03 June 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).

    Our construction work for the week commencing 03 June 2024 weather permitting includes:

    • From Fitzroy Street to Foveaux Street – continue paving works.
    • From Fitzroy Pl to Fitzroy Street – footpath, kerb and gutter works.
    • From Albion Street to Campbell Street (outside 285A Crown Street) – bus shelter removal, electrical works for lighting poles installation and footpath works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 27 May 2024

    Construction works continue at Crown Street between Albion Street to Foveaux Street (east) and between Albion Street to Campbell Street (west).

    Our construction work for the week commencing 27 May 2024 weather permitting includes:

    • From Fitzroy Street to Foveaux Street – electrical works, footpath excavation and paving works.
    • Fitzroy Pl – construction of continuous footpath treatment. Road closure set up will be in place, please follow detour route.
    • From Albion Street to Campbell Street – site set up and changes to parking for upcoming work at 285A Crown Street

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 13 May 2024

    Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).

    Our construction work for the week commencing 13 May 2024 weather permitting includes:

    • From Davies Street to Devonshire Street – paving footpath and continue work on 556 to 558 Crown Street driveway.
    • From Fitzroy Street to Foveaux Street – continue light pole installation works, footpath and kerb and gutter works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade project team

  • Construction update for week commencing 06 May 2024

    Construction works continue at Crown Street between Davies Street to Devonshire Street (east) and between Fitzroy Street to Foveaux Street (east).

    Our construction work for the week commencing 06 May 2024 weather permitting includes:

    • From Davies Street to Devonshire Street – paving footpath and continue work on 556 to 558 Crown Street driveway.
    • From Fitzroy Street to Foveaux Street – commence light pole installation works, footpath and kerb and gutter works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 29 April 2024

    Construction works continue at Crown Street between Albion Street to Campbell Street and between Davies Street to Devonshire Street (east). Our team is also ready to start section between Fitzroy Street to Foveaux Street (east).

    Our construction work for the week commencing 29 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – complete porous paving around the trees and work in the pits.
    • From Davies Street to Devonshire Street – paving footpath and commence work on 556 to 558 Crown Street driveway from Monday 29 April for up to 2 weeks (vehicles access will be restricted during works).
    • From Fitzroy Street to Foveaux Street - start site set-up including parking changes, light pole installation works

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 22 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).

    Our construction work for the week commencing 22 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue kerb and gutter works and continue footpath excavation.
    • From Oxford Street to Albion Street – work in the pits.
    • From Davies Street to Devonshire Street – continue kerb and gutter works and commence footpath works.

    Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 15 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street, between Oxford Street to Albion Street and between Davies Street to Devonshire Street (east).

    Our construction work for the week commencing 15 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue kerb and gutter works and commence footpath excavation.
    • From Oxford Street to Albion Street – trees installation
    • From Davies Street to Devonshire Street – commence kerb and gutter works and continue electrical work for light poles installation.

    Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 08 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street. We are also starting works from Davies Street to Devonshire Street (east).

    Our construction work for the week commencing 08 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue kerb and gutter works.
    • From Albion Street to Campbell Street – continue work on stormwater pipes near pedestrian crossing.
    • From Oxford Street to Albion Street – continue work on Telstra pits.
    • From Davies Street to Devonshire Street - start site set-up including parking changes and light pole installation works.

    Note: we are planning for a two week closure of 556 to 558 Crown Street driveway starting on Monday 29 April, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 02 April 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 02 April 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue footpath, kerb and gutter works.
    • From Albion Street to Campbell Street – continue work on stormwater pipes near pedestrian crossing.
    • From Oxford Street to Albion Street – continue work on Telstra pits.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 25 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 25 March 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue footpath, kerb and gutter works.
    • From Albion Street to Campbell Street – work on stormwater pipes near pedestrian crossing.
    • From Oxford Street to Albion Street – continue work on Telstra pits.

    No work will take place during the Easter Long Weekend.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 18 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 18 March 2024 weather permitting includes:

    • From Albion Street to Campbell Street – continue footpath, kerb and gutter works.
    • From Albion Street to Campbell Street - 333 Crown Street building driveway closure from Tuesday 19 March 2024.
    • From Oxford Street to Albion Street – work on Telstra pits.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 11 March 2024

    Construction works continue at Crown Street between Albion Street and Campbell Street and between Oxford Street to Albion Street.

    Our construction work for the week commencing 11 March 2024 weather permitting includes:

    • From Albion Street to Campbell Street – commence footpath works and continue kerb, gutter and footings for light pole installation.
    • From Oxford Street to Albion Street – light pole installation.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 04 March 2024

    Construction works continue at Crown Street between Albion Street to Fitzroy Place and will commence between Albion Street and Campbell Street.

    Our construction work for the week commencing 04 March 2024 weather permitting includes:

    • From Albion Street to Fitzroy Place – continue footpath, kerb, and gutter works.
    • From Albion Street to Campbell Street – continue footings for light pole installation.
    • From Albion Street to Reservoir Street – commence of kerb and gutter works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 26 February 2024

    Construction works are continuing Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.

    Our construction work for the week commencing 26 February 2024, weather permitting includes:

    • Continue 24 hours road closure at Clifton Reserve until 02 March 2024 for drainage and footpath works.
    • From Clifton Reserve to Albion Street and from Albion Street to Fitzroy Place – continue footpath, kerb, and gutter works.
    • From Albion Street to Campbell Street – footings for light pole installation.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 19 February 2024

    Construction works continue on Crown Street between Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.

    Our construction work for the week commencing 19 February 2024, weather permitting includes:

    • Clifton Reserve 24 hours road closure between 19 February 2024 to 02 March 2024 for drainage and footpath works.
    • From Clifton Reserve to Albion Street and from Albion Street to Fitzroy Place – continue footpath, kerb, and gutter works.
    • From 339 to 321 Crown Street – footings for light pole installation.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 12 February 2024

    Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.

    Our construction work for the week commencing 12 February 2024, weather permitting includes:

    • From 336 to 348 Crown Street – complete paving installation and asphalt work. Dismantle site.
    • From Clifton Reserve to Albion Street and from Albion Street to Fitzroy Place – footpath, kerb, and gutter works.
    • From 339 to 321 Crown Street - start site set-up including parking changes, potholing investigation works.

    Note: we are planning for a two week closure of Clifton Reserve starting Monday 19 February, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 05 February 2024

    Construction works on Crown Street between 336 Crown Street and Clifton Reserve is continue. We are also continuing works from Clifton Reserve to Albion Street, and from Albion Street to Fitzroy Place.

    Our construction work for the week commencing 05 February 2024, weather permitting includes:

    • From 336 to 348 Crown Street – paving installation and asphalt work.
    • From Clifton Reserve to Albion Street and from Albion Street to Fitzroy Place – footings, kerb, and gutter works.
    • From 277 to 265 Crown Street – work on Telstra pits.

    Note: we are planning for a two week closure of Clifton Reserve starting Monday 19 February, subject to approvals. Please contact the team if you are a resident and require a parking permit.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 22 January 2024

    Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.

    Our construction work for the week commencing 22 January 2024, weather permitting, includes:

    • Continue footpath works between Campbell Street and Clifton Reserve
    • Complete paving footpath works outside 320 to 332 Crown Street

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 15 January 2024

    Construction works on Crown Street Campbell Street and Clifton Reserve, nearby Crown Street Public School are underway.

    Our construction work for the week commencing 15 January 2024, weather permitting, includes:

    • Continue kerb, gutter and roadway works
    • Commence footpath works outside 320 to 332 Crown Street
    • Complete paving footpath works outside Crown Street Public School

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 8 January 2024

    Construction works on Crown Street between Campbell Street and Clifton Reserve.

    Our construction work for the week commencing 8 Juanuay 2024, weather permitting, includes:

    • Site set up with temporary fencing
    • Start parking changes
    • Start bus stop relocation
    • Start roadway and footpath construction works

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    We wish you and your loved ones a safe and happy holiday season. We look forward to a productive 2024 working with the Crown Street community.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 18 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve.

    Our construction work for the week commencing 18 December 2023, weather permitting, includes:

    • Continue roadway and footpath works
    • Commence paving footpath works

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    From 6pm Friday 22 December to Monday 08 January 2024 our project site and offices will be closed over the holiday period.

    We wish you and your loved ones a safe and happy holiday season. We look forward to a productive 2024 working with the Crown Street community.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 11 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve.

    Our construction work for the week commencing 11 December 2023, weather permitting, includes:

    • Continue drainage works
    • Continue kerb stone, concrete gutter and footpath works

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 04 December 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve.

    Our construction work for the week commencing 04 December 2023, weather permitting, includes:

    • Commence drainage works
    • Continue kerb and gutter works

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 27 November 2023

    Construction works on Crown Street between 354 Crown Street and Clifton Reserve.

    Our construction work for the week commencing 27 November 2023, weather permitting, includes:

    • Commence excavation of existing road and kerb and gutter.
    • Commence footing works.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 20 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street will end on Wednesday and our team will move to next section between 354 Crown Street and Clifton Reserve.

    Our construction work for the week commencing 20 November 2023, weather permitting, includes:

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 13 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 13 November 2023, weather permitting, includes:

    • 24 hour road closure at Arnold Pl intersection with Crown Street until 19 November for CFT construction
    • Flexi pave installation in tree beds at Crown Street between Campbell Street and Goulburn Street – temporary closure of outdoor dining spaces may be required.
    • Start work to dismantle temporary materials/equipment storage areas ahead of scheduled break in construction (Campbell Street - Oxford Street section) ahead of upcoming Christmas/New Year trading period.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 06 November 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 06 November 2023, weather permitting, includes:

    • Continue footing works at Crown Street between Campbel Street and Goulburn Street and between Oxford Street and Little Oxford Street
    • 24 hour road closure at Taggarts Lane intersection with Crown Street from 8 November until 11 November with detour via Little Oxford Street, Denham Street and Campbell Street
    • 24 hour road closure at Arnold Pl intersection with Crown Street from 8 November until 22 November for CFT construction

    Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 30 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 30 October 2023, weather permitting, includes:

    • Continue kerb, gutter and garden bed on Crown Street between Campbel Street and Goulburn Street
    • Continue footings for smartpole between Oxford Street and Little Oxford Street

    Paving to be rescheduled for finishing works in coming weeks at Taggarts Lane.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 23 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 23 October 2023, weather permitting, includes:

    • Reopening of Taggarts Lane
    • Continue excavation and prepare base for kerb and gutter on Crown Street between Campbel Street and Goulburn Street
    • Commence footings for smartpole between Oxford Street and Little Oxford Street and between Goulburn Street and Arnold Pl

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update for week commencing 16 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 16 October 2023, weather permitting, includes:

    • 24 hour road closure at Taggarts Lane entrance from Crown Street until 30 October with detours via Little Oxford St, Denham St and Campbell St in place
    • Continue drainage works within Taggarts Lane closure and commence CFT works.
    • Commence paving works between Goulburn Street and Arnold Pl
    • Continue excavation and prepare base for partial footpath on Crown Street between Campbel Street and Goulburn Street
    • Commence paving works between Campbel Street and Goulburn Street
    • Commence drainage works at Little Riley Street

    PROGRESS OF WORKS:

    Oxford to Campbell, October 2023

    Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction update - Week commencing 09 October 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 09 October 2023, weather permitting, includes:

    • 24 hour road closure at Taggarts Lane entrance from Crown Street until 30 October with detours via Little Oxford St, Denham St and Campbell St in place
    • Continue drainage works within Taggarts Lane closure
    • Continue excavation and prepare base for existing kerb, gutter and roadway between Goulburn Street and Arnold Pl
    • Commence footway works between Goulburn Street and Arnold Pl
    • Continue excavation and prepare base for kerb, gutter and partial footpath on Crown Street between Campbel Street and Goulburn Street

    Resident access will be available during the Taggarts Lane road closure, as well as access for Zest Apartments carpark and garbage collection.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Construction work update - week commencing 4 September 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    We are currently working along the southbound parking lane and footpath between 288 Crown Street and Campbell Street.

    Our construction work for the week commencing 4 September 2023, weather permitting includes:

    • Continue partial footway, kerb and gutter works between Taggarts Lane and Campbell Street
    • Continue paving from corner of Little Oxford Street to Campbell Street
    • 24 hour road closure at Taggarts Lane from Crown Street on 7 September to 6 October with detour via Little Oxford St, Denham St and Campbell St
    • Commence drainage and trenching works across Taggarts Lane
    • Remove barriers and begin site set-up across the road in the parking lane between 265 Crown Street and Campbell Street
    • Commence partial footway and roadway works within noise-reducing echo barriers between 265 Crown Street and Campbell Street

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access. Residential access will be available during the Taggarts Lane temporary road closure, as well as access for Zest Apartments carpark and garbage collection.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Thank you,

    Crown Street Upgrade team

  • Our construction work for the week commencing 7 August 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing. We are currently working along the southbound parking lane between Little Oxford Street and Taggarts Lane.

    Our construction work for the week commencing 7 August 2023, weather permitting includes:

    • Continue site set up along Crown Street towards Taggarts Lane
    • Excavation of existing kerb, gutter and roadway in the parking lane
    • Continue trenching along the parking lane within site set up
    • Install conduits and pits
    • Backfill and prepare base for kerb stone

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated.

    Please get in touch with the Community Liaison team with any questions or concerns.

    Regards,
    Community Liaison Team

  • Construction work update week of 24 July 2023

    Construction works on Crown Street between Oxford Street and Campbell Street are continuing.

    Our construction work for the week commencing 24 July 2023, weather permitting includes:

    • Continue site surveying
    • Continue installing tree protection zones
    • Set up barriers in the parking lane closest to our work area
    • Start work to saw cut concrete (in parking lane) into sections from Little Oxford Street to Taggarts Lane
    • Start excavation of underground drainage line in the parking lane.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

    For more information visit the Crown Street Upgrade website.

    Your patience and cooperation during this period are much appreciated. Please get in touch with the Community Liaison team with any questions or concerns.

    Kind regards,

    Community Liaison Team

  • Our construction work for the week commencing 17 July 2023

    Construction works on Crown Street between Oxford Street and Campbell Street will commence on Monday 17 July 2023.

    We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to vehicle parking, changes to pedestrian access and temporary lane closures.

    Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, and business and car users. Please follow the directions of traffic controllers at all times.

    Your patience and cooperation during this period are much appreciated.